
Construction work on two subroads in Bait-ul-Muqadas Mosque, located in the 30th section of District 7 is nearing completion. The project, which was launched earlier by Kabul Municipality with support from UNOPS, has reached its final stages.
The project spans a total length of 720 meters with widths of 4 and 5 meters and is being carried out to improve access for residents and generate employment opportunities.
The project also includes the construction of a culvert measuring 5.5 meters in length and 2.5 meters in width, along with a drainage system, which are expected to be completed soon.
Construction of Two Sub-roads Nearing Completion in the 30th Section of District 7
