In District 20, construction activities on the 4th section of Gull Bagh Road are currently in progress, extending from the Chehil Dukhtaran area to the Kabul–Logar Road.
The road is 2,422 meters in length and 33 meters in width, and the project also includes the construction of drainage system with widths ranging from 50 centimeters to one meter. As part of the plan, 11 culverts, pedestrian walkways, flowerbeds, street lighting, road markings, and other standard road facilities are being implemented.
According to the schedule, the construction of this road is expected to be fundamentally completed within the next eight months.