Kabul Municipality’s Directorate of Work Maintenance and Monitoring is carrying out the third and final asphalt layer on the third section of the Khair Khana Kotal Road, extending from Sarai Shamali Intersection to the upper part of Khair Khana Kotal.
Engineer Mohammad Nasir Samadi, the project manager, said that the asphalt paving is being carried out in accordance with technical and engineering standards. He added that efforts are underway to complete the remaining works as soon as possible and reopen the road to traffic.
The Khair Khana Kotal Road development project covers a length of 3,647 meters and a width of 27 meters. So far, the first and second asphalt layers have been completed on a 2,430-meter section, while the final asphalt layer is currently being applied.
According to the project manager, approximately 1,217 meters of the road remain to be completed, and asphalt paving on this section will begin after the required base works are completed.
Khair Khana Kotal Road is one of Kabul’s key transportation routes, used daily by thousands of vehicles and passengers.
Upon completion, the project will increase the road’s traffic capacity, reduce congestion, and provide residents with safer, faster, and more convenient transportation.